|
APX is pleased to provide you with the latest ERCOT
information to keep you informed of on-going market activities.
Legislative and Regulatory Issues of
Interest
Some of the most important actions taken by the Texas Legislature
and/or the Public Utility Commission of Texas (PUCT) during the last few
weeks are:
In March 2008, APX released an early version of the APX MarketSuite to
ERCOT clients to facilitate client participation in Texas Nodal testing
and market simulation. APX will expand and enhance the APX MarketSuite to
support the ERCOT Texas Nodal Market Trials later this year with an
anticipated go-live date scheduled for late 2010. There will also continue
to be enhancements to the APX MarketSuite in both the CAISO and ERCOT
markets, based on APX experience and client input. More on ERCOT Nodal is
provided in other sections of this issue.
- Legislative Activities: The
Legislative Session began with a hope to have significant improvement in
advancement of clean coal technology, higher energy efficiency goals,
and increasing goals for renewable resources with particular attention
to solar power production. However, the Session completed its work on
June 1st without passing many electric power related bills. Some of the
few electric power related bills that passed both Texas Houses are
summarized below:
Clean Technology:
- HB 469 (Representative King, et al. and Senator
Seliger) passed both Houses with some modification and sent to the
Governor. Its main purpose is to encourage the development of clean
coal technology. In particular, the bill requires the Texas
Comptroller of Public Accounts to adopt rules for issuing to an entity
implementing a clean energy project, which is implemented in
connection with the construction of a new facility, in this state a
franchise tax credit. Several conditions should be met for a project
to be eligible for this franchise tax credit and the total amount is
capped at the lesser of a) 10% of the total capital cost of completing
the project (excluding financing charges) or b) $100 million.
- HB 1796 (Representative Chisum and Senator
Watson) passed both Houses with some modification and sent to the
Governor. Its main purpose is for the commissioner of the Texas
General Land Office to adopt standards for the location, construction,
maintenance, monitoring, and operation of a carbon dioxide repository.
The commission shall ensure that the construction, maintenance,
monitoring, and operation of the carbon dioxide repository comply with
the requirements that may be set by the U.S. Environmental Protection
Agency regarding carbon dioxide sequestration. This section also
requires annual report regarding the carbon dioxide
repository.
This bill also expands the definition of "Advanced
clean energy project" qualified to receive grants or other incentives
to include those projects that capture not less than 50 percent of the
carbon dioxide in the portion of the emissions stream from the
facility that is associated with the project and sequesters that
captured carbon dioxide by geologic storage or other means.
- HB 1783 (Representative Solomons, et al. and
Senator Fraser) passed both Houses with some modification and sent to
the Governor. Its main purpose is to require both the Public Utility
Commission of Texas (PUCT) and Electric Reliability Council of Texas
(ERCOT) make publicly accessible without charge live Internet video of
all public hearings and meetings they hold for viewing from their
Internet websites. The commission may recover the costs of
administering this section by imposing an assessment against
non-consumer market participants.
- HB 3309 (Representative Gattis and Senator Ogden)
passed both Houses with some modification and sent to the Governor.
The main purpose of this bill is to allow the Commission to consider
an application filed by a person not currently certificated as an
electric utility for a certificate of convenience and necessity to
construct transmission capacity that serves the ERCOT power region.
The applicant should meet certain conditions before being granted a
certificate under this section. This section also allows the
Commission to consolidate proceedings on applications to obtain or
amend several certificates of convenience and necessity for the
construction of transmission lines that share a common point of
interconnection.
Retail Customers: A few bills passed both
Houses to assist retail customers to make an informed decision regarding
their retail choices, including the followings:
- HB 1799 (Representative Bohac, et al. and Senator
Eltife): This bill requires the following statement be added to the
monthly bills: "For more information about residential electric
service please visit www.powertochoose.com."
- HB 1822 (Representative Solomons, et al. and
Senator Fraser): This bill requires that the applicable terms be
labeled uniformly on each retail bill sent to a customer by a
certificated telecommunications utility, retail electric provider, or
electric utility to facilitate consumer understanding of relevant
billing elements. In addition, Retail Electric Providers are required
to provide residential customers who have fixed rate products with at
least one written notice of the date the fixed rate product will
expire. The notice must be sent to the customer's billing address by
mail or e-mail address at least 30, but not more than 60, days
preceding the date the contract will expire.
Competition for Non-ERCOT Areas within Texas:
The following two bills were passed both Houses to delay retail
electricity competition in areas served by Southwestern Electric Power
(SWEPCO) and Entergy:
- SB 547 (Senator Eltife): The bill concluded that
SWEPCO is unable at this time to offer fair competition and reliable
service to all retail customer classes in its Texas service territory
and mandated delay until certain conditions are met. The Commission is
required to evaluate necessary steps taken by SWEPCO to open its
service territory to retail competition.
- SB 1492 (Senator Williams): Entergy is ordered to
cease all activities relating to the transition to competition within
Texas. It is also required to propose a competitive generation tariff
to allow eligible customers the ability to contract for competitive
generation. The commission shall approve, reject, or modify the
proposed tariff not later than September 1, 2010.
Other ERCOT-Related Bills: Two important
ERCOT related proposed bills did not pass by this session. The first one
was HB 1959 (requiring the Sunset Advisory Commission
to conduct a special-purpose review of the Electric Reliability Council
of Texas as part of the commission's review of the Public Utility
Commission of Texas for the 82nd Legislature) that was passed by both
Houses but failed to be finalized. The second one was HB 2421
(to refine the governance of ERCOT by requiring nine
Independent Board Members) that was passed by the House of
Representatives but could not be finalized by the end of this Session.
Given the intent of the Texas Legislation, we may see some attempts by
the Commission to address the issues reflected by these proposed bills.
- Docket No. 36416, AEP Energy Partners' Appeal of
the Decision of the ERCOT Board Assigning Oklaunion Generating Station
to the West Zone and Request for Expedited Consideration and Emergency
Remand with Instructions. In a decision on October 21, 2008,
the ERCOT Board followed a recommendation by the Technical Advisory
Committee and finalized zones for implementation in 2009. The decision
resulted in American Electric Power's Oklaunion power plant to be
included in the West Zone rather than in the North Zone. In making this
decision, the Board relied on ERCOT staff recommendation to choose
Scenario 3i rather than Scenario 3h that was originally recommended to
the Technical Advisory Committee by the Wholesale Market Subcommittee
and would cluster Oklaunion power plant in the North Zone. AEP appealed
the decision to the Public utility Commission of Texas stating that if
"ERCOT staff and the Board followed the procedures and analysis that
have been established and followed in applying and interpreting Section
7.2 of the ERCOT Protocols in previous cases, Scenario 3h would and
should have been approved." In addition, AEP claimed that there were
several shortcomings in ERCOT's implementation of the procedure and
violation of Protocols and requested the Commission to remand this case
back for further consideration.
This case attracted various
stakeholders with clear majority defending the action by the Board and
recommending the Commission to deny AEP's appeal. These parties
acknowledged some shortcomings in the implementation of procedures to
determine zones, however, they concluded that the overall decision was
based on solid evidence and analysis and resulted in appropriate
determination of zones for 2009. In a two to one decision, the
Commission agreed with these parties and decided to deny AEP's appeal in
its May 21, 2009 Open Meeting. Furthermore, the Commission clearly
expressed its dissatisfaction with the way ERCOT implemented its
procedures and ordered ERCOT to take necessary steps in a timely manner
to clarify the Protocols to prevent such shortcomings to influence
future decisions. ERCOT and its stakeholders are working to develop
refinements to the Protocols for the Board consideration in its July 21,
2009 meeting.
- PUCT Investigation Cases and Compliance
ERCOT Nodal Update: TPTF Is Replaced
with the Nodal Implementation Team and ERCOT Is Expected to Finalize Its
Contract Renegotiations with Vendors Soon
Mike Clearly, Senior Vice President and Chief Technology Officer,
regularly attends various ERCOT meetings, particularly monthly meetings of
the Technical Advisory Committee and Board of Directors, to update various
members on progress in the Nodal Project. He describes the timeline,
status of various components of Nodal Project, and how defects and delays
are handled by ERCOT to ensure the Nodal Implementation Project is to be
completed within the budget and schedule approved by the Board. The main
nodal-related points from the recent meetings are provided below:
- In the June 4th TAC meeting, Mike introduced a new phrase, ERCOT
Enhanced Reliability & Markets (EERM), to be used by ERCOT
internally to cover both current Zonal operation as well as Nodal
implementation. In his view, reliability includes Network Model
Management System (NMMS), Energy Management System (EMS), and Operation
System (OS) Projects while Markets include Market Management System
(MMS), Congestion Revenue Right (CRR), and Commercial System (COMS)
Projects. Then, he provided the recent Nodal Team staff additions to
enhance program success. He emphasized on the importance of
participants' readiness and informed TAC members that Vikki Gates has
joined Nodal Team to lead ERCOT & Market Readiness activities,
including the issue of "Parking Lot" that includes additional proposed
revisions to the Nodal protocols that will be implemented after Go-Live
date. Vikki is expected to have more detailed plan by July 19, including
the name of ERCOT staff responsible for various tasks.
Mike also
added that Betty Day (who has been with ERCOT for nine years) will lead
Program Control & Review to ensure proper traceability of what will
be implemented. This will be in fact an internal auditing job to ensure
success in Nodal implementation. To enhance her work, several new staff
are added, including the addition of Bob Spangler (formerly with
Luminant) and Floyd Trefny (formerly with Reliant), who both were very
active in ERCOT Nodal development in the last several years and will be
the Subject Matter Experts to assist ERCOT to ensure that what is
proposed in the Nodal Protocols will be actually implemented to minimize
any potential deviations.
- In June 16 Board meeting, Mike acknowledged that only six out of
thirteen tracking milestones scheduled for May were completed, however,
he did not believe the resulting delays would have any impact on Nodal
timeline and budget. However, he acknowledged that these delays will
have some impacts on the budget. Currently, ERCOT plans to fully
implement nodal design by December 1, 2010 at an estimated cost not to
exceed $660 million. The latest estimated cost is $644 million and is
expected to be further refined for July Board meeting after ERCOT
completes its renegotiations with vendors by the end of June. Mike
further reminded Board members of the overall risks facing Nodal
project. The main points were:
- Complete Integration System (Expected on 2-12-10): Resource
availability remains a big risk factor.
- The main risk facing Market Trials (Expected to begin on 2-12-10)
remains to be reconciling Protocols, Systems and Market Expectations.
Nodal Team is acting proactively to ensure that the final system is
consistent with stakeholders' approved Nodal Protocols.
- The main risk facing Go-Live (Expected on December 1, 2010) is the
possibility of not having adequate Data Center capacity and integrity
of Single Entry Model (SEM) data provided by Market Participants.
Nodal Team is aware of this potential and is taking steps to eliminate
this risk.
- Nodal Implementation Team (NIT): In its June 4th meeting, TAC
finalized its decision to establish a good replacement for Transition
Plan Task Force (TPTF). TAC considered a proposal that included nine
members representing seven segments (with Customers have three
representatives with 0.5 vote each) and required monthly meetings with
the public participation. NIT will also have frequent meetings within 24
hours whenever ERCOT requests for Market Participants' inputs. All
decisions by NIT will be based on simple majority vote. Among NIT's core
responsibilities are 1) assuring that Market Participant's interface
software and ERCOT systems operate within the intent of the Nodal
Protocols in a production environment and 2) evaluating Market
Participant readiness metrics and scorecards. NIT is a Subcommittee
under the Technical Advisory Committee and reports to TAC on monthly
basis. The main concern was to further clarify ways to address any
potential gap that may be found between the intended Nodal protocols and
the latest software version. A decision was made to approve the creation
of this new TAC Subcommittee with the first meeting set for June 22,
2009 when the representatives of various segments will elect a Chair and
Vice Chair.
Finally, ERCOT has indicated August 31, 2009 as its Single Entry Model
(SEM) Go-Live date. To facilitate expected work by Market Participants,
ERCOT continues its regularly scheduled Thursday afternoon weekly meetings
with stakeholders to share more details before SEM Go-Live date. As
envisioned by the current Procedure, ERCOT will seek approvals from
NIT/TAC/BOD prior to SEM Go-Live. Meanwhile Market Participants should
continue to support required activities including telemetry, network
model, and other activities needed for ERCOT to enhance its nodal
implementation. In particular, ERCOT has already scheduled the following
Focused Input Testing (FIT) for the next few weeks:
| ALL TIMES ARE
CENTRAL |
| Duration |
State date
and time |
End date and
time |
| 27 hrs (3x9) |
June 30 - 8:00 am |
July 2 - 5:00 pm |
| 27 hrs (3x9) |
July 14 - 8:00 am |
July 16 - 5:00 pm |
| 27 hrs (3x9) |
July 28 - 8:00 am |
July 30 - 5:00
pm |
The Electric Reliability Council of Texas issued several reports in the
last few weeks. Summaries of main points in three reports are provided
below:
- ERCOT Carbon Study: In response to a
request by the Chairman of the Public Utility Commission of Texas, ERCOT
filed a report with the Commission on May 12, 2009 titled "An Analysis
of Potential Impacts of CO2 Emission Limits on Electric Power Costs in
the ERCOT Region". ERCOT performed several scenarios under various
assumptions on key variables such as natural gas prices, various levels
of energy efficiency achievements, and various levels of renewable
generation resources. In addition, different carbon allowance costs
($/ton) were assumed to calculate the impacts on total annual wholesale
power cost and wholesale power prices. The main findings are summarized
below:
- In the reference case, with $7/MMBtu natural gas prices, expected
load levels and the existing and committed level of wind and other
generation, the carbon allowance costs must rise to between $40 and
$60 per ton in order to reduce carbon emissions from electric
generation in ERCOT to 2005 levels by 2013. This level of allowance
costs would result in an annual increase in wholesale power costs of
approximately $10 billion and would increase a typical consumer's
monthly bill (for 1,000 KWh) by $27. Higher natural gas prices at
$10/MMBtu would result in an increase in wholesale power costs of
approximately $20 billion. At such level, a much higher carbon
allowance costs, well above $60 per ton, is required to achieve
desired emission reductions.
- Total CO2 emissions are reduced below 2005 levels at a carbon
allowance price between $25 and $40 per ton at $7/MMBtu natural gas
price if total energy use was reduced by 10%. This level of allowance
costs would result in an annual increase in wholesale power costs of
approximately $7 billion. At this allowance cost, a typical consumer's
monthly bill would increase by $17.
- The additional CREZ wind generation allows the targeted emissions
reductions to be met at a lower allowance cost. At $7/MMBtu gas, the
2005 carbon emissions levels are met at an increase in annual
wholesale power costs of approximately $7 billion. At this allowance
cost, the increase in a typical consumer's monthly bill would be $22.
- The combination of additional CREZ wind and lower energy usage
results in smaller increases due to CO2 emissions limits in both
wholesale power costs and the typical consumer's monthly bill at a
$7/MMBtu gas price, as compared to the reference case.
The full report is available at the the Commission
website.
-
ERCOT 2008 Annual Report on the Texas Renewable
Energy Credit Trading Program: The Public Utility Commission of
Texas requires ERCOT to file its Annual REC Report by May 15. ERCOT
filed its REC Report on May 13, 2009 under the Commission Project No.
27706. The Report indicated significant increase in renewable generation
capacity in the REC Program during 2008 with 93 REC generation accounts
and an installed capacity of about 8,600 MW which includes a total of
six Offset generator accounts with a total capacity of about 298 MW. In
addition, these resources accounted for over 17 million MWh of energy
generated in 2008, an increase of about 70% over 2007 renewable
generation. Wind resources accounted for about 95% of total renewable
generation in 2008. The total adjusted REC requirement for all Retail
Entities for 2008 as required by the Commission was 6,747,162 RECs. The
difference between generated REC and its mandatory requirements could be
banked for future use or offered into the voluntary market. Based on
recently declassified data for 2007, Reliant, TXU Energy, and
Constellation Energy were ranked the top three Retail Entities regarding
REC requirements. The Report also listed the total amount or REC retired
in 2007 for Mandatory and Voluntary markets as 3.4 million and 1.6
million, respectively. Full Report could be found under Project No.
27706 at PUC of Texas Interchange site.
- May 2009 Report On The Capacity, Demand, And
Reserves In The ERCOT Region: ERCOT prepares an annual resource
adequacy assessment in May with an updated in December of each year. The
latest Report was published on May 29, 2009 indicating adequate capacity
within ERCOT Region above the minimum 12.5% target reserve margin
throughout the forecast period, 2009 through 2014. The report also
indicated other resources, including significant amount of mothball
capacity, that could be relied upon if need arises. Full Report is
available on the ERCOT
website.
| MW |
2009 |
2010 |
2011 |
2012 |
2013 |
2014 |
| Firm Load Forecast |
62,266 |
62,699 |
64,137 |
66,037 |
68,042 |
69,480 |
| Resources |
72,712 |
75,314 |
76,215 |
77,287 |
79,122 |
79,122 |
| Reserve Margin |
16.8% |
20.1% |
18.8% |
17.0% |
16.3% |
13.9% |
Planned Units in Full Interconnection
Study Phase |
0 |
7,858 |
15,417 |
21,116 |
23,722 |
25,463 |
Participation in June-September
Auction for the Emergency Interruptible Load Service (EILS) Shows Some
Comeback
On May 19, 2009, ERCOT released the latest results of its procurement
of EILS covering the Contract Period of June 1 through September 30, 2009.
In contrast to the low amount of EILS offers in previous Contract Period
(February-May), ERCOT received more offers in this period and prices are
noticeably lower by a few dollars in average. ERCOT reported the following
results:
February through May 2009
Contract Period Total Cost for this Period: $6,361,774
|
| Time
Period |
Business Hours
1 |
Business Hours
2 |
Business Hours
3 |
Non-Business
Hours |
| Definition |
8 AM to 1 PM
Mon-Fri except Holidays |
1 PM to 4 PM
Mon-Fri except Holidays |
4 PM to 8 PM
Mon-Fri except Holidays |
All other
Hours |
| EILS
Procured |
276.4 MW |
154.7 MW |
237.3 MW |
255.6 MW |
| No. of EILS
Resources |
47 (includes 34
aggregations) |
34 (includes 22
aggregations) |
50 (includes 34
aggregations) |
46 (includes 30
aggregations) |
| Avg. Cost (per MW per
Hour) |
$8.64 |
$8.29 |
$9.90 |
$8.66 |
| Projected
Cost |
$1,027,435.55 |
$330,856.62 |
$808,426.49 |
$4,195,055.47 |
As reported by ERCOT, the total projected year-to-date cost of EILS
programs is $10.87 million. EILS resources are paid as bid if selected and
are dispatched through Verbal Dispatch Instruction to Qualified Scheduling
Entities where participants must have their interruptible load available
during at least 95% of the hours in their committed time periods. The
Commission rule allows up to $50 million in annual (February through
January) EILS program costs, however, it is completely up to ERCOT to
reject offers that may not look reasonable or economical. For more
information on EILS program and other related documents see the ERCOT
EILS web page.
See APX Experts in Upcoming Power and
Environmental Market Events
APX Experts are actively covering different power and environmental
markets issues in several conferences and workshops. The followings may be
of interest to you:
- June 23, 2009
32nd International Association
for Energy Economics (IAEE) International Conference, "Energy, Economy,
Environment: The Global View." San Francisco, CA - Grand Hyatt
Hotel Session Chair - Dr. Parviz Adib, Director, presiding a session
entitled: Alternative Paths to Achieving Environmental
Goals http://www.usaee.org/USAEE2009/
- June 24, 2009
32nd International Association
for Energy Economics (IAEE) International Conference, "Energy, Economy,
Environment: The Global View." San Francisco, CA - Grand Hyatt
Hotel Speakers - Dr. Reiner Musier, Chief Marketing Officer and Dr.
Parviz Adib, Director, presenting a paper on The Role of Technology
in Markets for Environmental Tradable Permits http://www.usaee.org/USAEE2009/
If interested, you can find about this and other events by going
through APX website.
About APX, Inc. APX provides technology, strategic
consulting, and expert operational services to assist wholesale power
market participants reduce costs and improve performance in power
scheduling, settlement, market operations, and demand response programs.
Clients include utilities, merchant companies, financial institutions,
retail service providers, ISOs/RTOs, and other electricity market
participants.
APX is also the leading infrastructure provider for
environmental and energy markets in renewable energy and greenhouse gases
including carbon commodities. Providing a bank and mint for environmental
commodities, APX solutions are trusted to create, track, manage, and
retire renewable energy certificates (RECs), energy efficiency and
conservation certificates, carbon offset credits such as verified
emissions reductions (VERs), and greenhouse gas emission allowances.
More information is available at www.apx.com or contact us at 408.517.2100.
|